Sailboat Circle Drainage Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Status: Under Construction

NEW:   
Construction Update OPEN HOUSE FOR RESIDENTS

Wednesday, September 27, 2023
6PM - 8PM
Stop in anytime during this time period
Weston City Hall, 17200 Royal Palm Boulevard, Weston, 33326


Project construction began Monday, May 8, 2023 and the new schedule for completion will be by the end of the year. 

aerial image of Sailboat Circle drainage repair map area

 

 

 

 

 

 

 

 

 

 

 

 

 

An Open House for residents was held on Dec. 14, 2022.

The City is implementing the re-construction of stormwater retention swales in the entire neighborhood located along Sailboat Circle. 

The project scope includes the following: 

  • excavation
  • lowering, and
  • re-grading of swale areas
  • installation of addition drainage pipe and structures
  • sod and restoration

HIGHLIGHTS: 

Project - Sailboat Circle Roadway Drainage Improvements (Surtax Funded R&M Project #BC-WESTON-FY2020-00001)

  • Est. Project Cost - $550,000

  • Status - Under Construction

  • Traffic Impacts - Lane Closures within Project limits with access to local traffic when contractor is working.

  • Project Benefits - This project will alleviate the localized flooding on the roadway, sidewalk, and individual driveways in the neighborhood. 

Schedule - Completion anticipated in December 2023

SailboatCircle_Image of flooding & neighborhood Map